Government plans ZiG73.6 billion in capital spending in 2027, with roads, devolution, housing, dams and hospitals getting the biggest shares. The focus is on finishing projects already started, such as the Gwayi-Shangani and Kunzvi dams and the Christmas Pass Bypass. Electricity is set to reach 558,335 more homes, lifting access from about 54% to 65%.
Who is affected
ZiG9 billion for roads plus US$400 million in planned bank financing for major highways, though only US$175 million is secured so far.
Targets to connect 558,335 new households to electricity and continued borehole drilling should improve daily life, especially in rural areas.
ZiG7.6 billion for housing and serviced stands, plus support for housing funds that help first-time buyers get mortgages.
ZiG970.9 million for irrigation and new dams like Gwayi-Shangani should help farmers cope with drought.
Contractors gain work, but payment delays and reliance on loans not yet secured could slow projects.
The big picture
Infrastructure means the shared things we all use: roads, dams, power lines, water pipes, clinics and schools. Government calls money spent on building them capital spending.
For 2027, the Budget sets capital spending at ZiG73.6 billion (US$2.6 billion). The 2027 Infrastructure Investment Programme explains how it will be used.
The main rule this year is simple: finish what was started. Treasury says there is a "huge stock of stalled and ongoing projects". So money goes first to projects that are nearly done, rather than spreading it thinly over new ones.
Where the money goes
| Area | 2027 allocation | Main aim |
|---|---|---|
| Local authorities (devolution) | ZiG17.5 billion | Local roads, clinics, schools and water, chosen by councils |
| Roads | ZiG9 billion | Rehabilitation and upgrading of the road network |
| Housing and social amenities | ZiG7.6 billion | Houses, flats and serviced stands |
| Dams | ZiG4.3 billion | Gwayi-Shangani and Kunzvi-Musami |
| Health | ZiG3.9 billion | Hospitals and new primary care facilities |
| Higher education | ZiG2.1 billion | Universities, colleges and polytechnics |
| Irrigation | ZiG970.9 million | Repairing and finishing irrigation schemes |
| Boreholes | ZiG418.7 million | Presidential Borehole Drilling Programme |
The devolution money equals 5% of expected revenue. It goes straight to councils and rural district councils for local projects.
Roads
- ZiG9 billion is set aside for the Road Development Programme.
- Government has arranged for local banks to raise US$400 million for major roads, including Harare to Masvingo, Harare to Beitbridge, Harare to Chirundu and Bulawayo to Victoria Falls. So far US$175 million is secured and US$75 million paid out.
- The 31.2 km Christmas Pass Bypass in Mutare is 36% complete and due by mid-2027. It will take heavy trucks off the dangerous pass and out of Mutare's town centre.
- In Harare, the Mabvuku Interchange is 89% complete.
- On the Bulawayo to Victoria Falls road, 68.4 km have been finished and opened to traffic.
Electricity
- New projects over the last two years added 600 MW, bringing capacity to 3,412 MW. There is still a gap of about 500 MW.
- Hwange Unit 5, idle since 2021, should be repaired in 2027, adding 160 MW.
- Batoka Gorge on the Zambezi could produce 2,400 MW, shared with Zambia. Each country has committed US$220 million in equity. The 2027 Budget includes US$25 million as Zimbabwe's first contribution.
- Government aims to connect 558,335 new households in 2027, raising access to electricity from about 54% to 65%. Roughly 37% of new connections will be mini-grids or home solar.
Water and dams
- Gwayi-Shangani Dam, which will supply Bulawayo, has its wall 83% complete. The wall, pump station and a small power plant should be finished in 2027.
- Kunzvi Dam, for Greater Harare, is 77% complete and has started holding water.
- In 2026, 1,213 boreholes were drilled. Rural access to improved water rose from 72% in 2020 to 81% in 2026.
Homes, clinics and schools
- Housing: ZiG7.6 billion for houses, flats and serviced stands. Government will also put money into the Housing Guarantee Fund and National Housing Fund to help first-time buyers get mortgages.
- Health: Plans include 26 new primary care facilities, two new urban district hospitals in Harare and Bulawayo, finishing Lupane and Masvingo provincial hospitals, and solar power for 2,000 public health facilities. Manyame Hospital is a priority to open fully.
- Schools: The focus is more classrooms to ease overcrowding, water and toilets, and finishing projects already under way. Government will also work with banks and pension funds to finance new schools.
What this means for you
- Jobs: Building roads, dams and houses needs labour, from builders to truck drivers to food vendors near sites. The programme does not give a jobs number, so treat big promises with care.
- Daily travel: Better highways and the Mutare bypass should mean safer, quicker trips and less wear on kombis and trucks.
- Power at home: If the connection target is met, many rural families will switch on lights for the first time.
- A worked example: Think of a family building a house over several years. If they keep starting new rooms, none get a roof. If they finish one room at a time, they can move in. Government is now trying to finish rooms before starting new ones.
The catch
Some of this depends on loans and private money that is not yet in hand. Only US$175 million of the US$400 million road financing is secured. Batoka still needs financing to be finalised. And contractors are owed money from past work, which has slowed projects before.
Bottom line
The 2027 plan puts real money into roads, power, water, housing and health, with ZiG73.6 billion in capital spending. Its best feature is the focus on finishing big projects like Gwayi-Shangani, Kunzvi and the Christmas Pass Bypass. Whether ordinary people feel the benefit depends on money arriving on time and contractors being paid.
Source: 2027 Zimbabwe Infrastructure Investment Programme and 2027 Budget Statement, Ministry of Finance